OUTAGE-2022 IS BEING IMPLEMENTED IN ACCORDANCE WITH THE ENVISAGED SCHEDULE

15.06.2022

OUTAGE-2022 IS BEING IMPLEMENTED IN ACCORDANCE WITH THE ENVISAGED SCHEDULE

Outage activities are being implemented at the ANPP from April 16, 2022. According to the established network schedule, all the planned work related to the safety systems and major equipment has been completed for now.

Within the established period a reactor intermediate maintenance with core refueling was implemented.

The activities aimed at modernization of the emergency core cooling system were completed.

To ensure more reliable and failsafe operation of the system, 2 of the 6 previous high-pressure pumps have been replaced with low-pressure pumps which will increase the system's core cooling ability at low pressure in the primary circuit.

As part of the outage the turbogenerator auxiliary equipment and their control panels were upgraded and maintenance of the circulating water supply system of the turbine condensers was performed.

Cooling tower №1 upgrading activities are underway.

The work is being carried out according to the established schedule. After relevant tests and checks, on the basis of a license issued by the RA Committee for NSR, Unit 2 will be connected to the RA grid.